Installing the Battery Temperature Sensor
975-0540-01-01 Revision B 2–21
This guide is for use by qualified personnel only.
4. Pass the other end of the BTS cable through the knockout and strain relief
bushing on the charge controller, and then insert the BTS plug into the BTS
RJ-11 port. See Figure 2-15.
5. Replace the charge controller’s wiring compartment cover.
Figure 2-14 Attaching the BTS to a battery terminal
HAZARD OF ELECTRIC SHOCK
The BTS cable must not pass through the same conduit used for PV wiring and
battery cables.
Failure to follow these instructions can result in death or serious injury.
Figure 2-15 Installing the BTS
Insert the BTS plug into
the charge controller’s
BTS port.
Attach the BTS to a
battery terminal or to
the side of a battery.