7. Commissioning
7.1 Necessary devices and documents
Devices
• A universal measuring instrument (voltage, current, resistance,
diode).
• A PC and the configuration tool, if the configuration is done
WARNING!
Do not use an isolation resistance
meter for measuring resistance!
• This Installation and Commissioning manual.
• Operation manual.
• Planning and installation documents for the project.
• Client/project configuration data if the configuration is done
when commissioning.
Note!
The system does not require
configuration in order to function.
On the other hand, client specific
features may require configuration.
7.2 Order of commissioning
1. Check that the installation has been done correctly according to
the plans.
2. Make preliminary checks on the control panel.
3. Test run the control panel.
4. Connect detector loops.
5. Connect monitored output lines.
6. Make site specific settings.
7. Connect the outputs.
8. Connect the inputs.
9. Connect the serial communication ports.
10. Configure the system if required according to the plan or site
specific features.
11. Connect the router to the defined control panel.
For SLC only (System Sensor
devices).
If the system is not configured and a
loop has the same addresses for
both detectors and I/O-modules, the
detectors will be assigned
addresses from the low range
(01…159) and the I/O-modules from
the high range (201 and 359).
Usually it is easier to start up loops,
if the control panel is not configured.
Note!
On ALCA / ALCB - loop (Intellia
devices) all detectors and modules
must have individual addresses