Planning Instruction 66571758GB0 Fire Detection 4
1.3 Regulations
EN54-14 “Guidelines for Planning, Installation, Commissioning and Maintenance” defines good general guidelines
for planning. Local specific regulations must also be followed.
The main planning and documentation phases are described in the diagram below. A typical lay out drawing
including devices is found in the section 1.4.
Schneider Electric Pelco Finland Oy
Kalkkipellontie 6, 02650 Espoo, Finland Telephone: +358 10 446 511 Fax: +358 10 446 5103 www.pelco.com/nordic
Document Number 66571758GB0 49 2011
© 2009 Schneider Electric. All rights reserved.
Initial concept
Initialisation and configuration
Assessment of needs or
Risk Assessment
Planning and design
Installation
Alteration,
modification or
extension
Commissioning and verification
Third party approval and/or handover
Third party periodical inspection
Use
End user
Maintenance
Planning
Maintenance
Installation
Commissioning
Standard EN54-14: Guidelines for planning